Terms may be either:
Conditions: go to the route of the contract.
Remedy: elect to terminate/affirm contract or to claim damages. NB this election is binding. If elect to sue for damages cannot later request performance.
Warranties: terms of less importance
Remedy: damages only.
Innominate Terms: terms that are neither conditions nor warranties
Remedy: if the breach deprives the innocent party substantially the whole benefit of the contract then a right of election. If not then only damages are available.
Electing to Terminate/Affirm
No controls on making this election
Professor Brownsword suggests six reasons one might wish to terminate:
1) Breach shows lack of commitment to contract.
2) Breach raises concerns about competence of other party
3) Breach renders the performance of the contract radically different
4) Proving losses arising from the breach puts the innocent party at risk.
5) Breach leads to concerns about other party’s ability to keep future promises.
6) Breach leads to concerns about innocent party’s ability to keep future promises.
Conditions:
Schuler v Wickman Machine Tool Sales (1974) – Wickman was to act as agent in obtaining buyers for panel presses manufactured by Schuler. Clause stated it was a condition for Wickman to send representative to solicit orders once a week, missed a few of these. Another clause gave right to terminate after 60days if a breach remained un-remedied. Schuler terminated.
Majority in HoL held that a few missed visits could be remedied, was not a condition.
Lord Wilberforce dissented: no basis for the assumption that the parties had adopted “a standard of easygoing tolerance rather than one of aggressive, insistent punctuality and efficiency”
Lord Reid: construction has an ordinary English meaning as well as the legal meaning.
Professor McKendrick The key to understanding this case lies in the relationship between clauses 7 and 11 of the parties’ contract. Lord Wilberforce would be right if just clause 7, but the contractual machinery in clause 11 meant that other interpretation justified.
Warranties:
Sale of Goods Act 1979 defines a warranty as “collateral to the main purpose of the contract”
Innominate terms:
Distinction above is based on the intention of the parties. But it may well be that a very important term could be breached in a very minor way, causing little loss, and vice versa.
Hong Kong Fir Shipping v Kawasaki (1962) – charterparty for 24months. Term required the vessel be fit for use (seaworthiness clause). Vessel was unfit for 20weeks as a result of engine trouble and incompetence of crew. Charters wrote to terminate contract.
Held, in seminal judgement of Diplock LJ, that seaworthiness clause was neither warranty nor condition.
The question was whether the breach “deprived the party not in default of substantially the whole benefit which it was intended that he should obtain from the contract”
NB it is NOT the case that an innominate term is effectively a condition if the consequences of its breach are serious, and a warranty if otherwise.
Threshold for termination is very high.
Reactions to Hong Kong Fir and Innominate Analysis:
The Mihalis Angelos [1971] – Charterparty Haiphong to Hamburg stated a date the ship was expected ready to load. In fact the ship was not.
CA was anxious to limit application of innominate...