xs
This website uses cookies to ensure you get the best experience on our website. Learn more

#10281 - Breach Of Contract Between Exchange And Completion - Property Law and Practice

Notice: PDF Preview
The following is a more accessible plain text extract of the PDF sample above, taken from our Property Law and Practice Notes. Due to the challenges of extracting text from PDFs, it will have odd formatting.
See Original

(Prop. Law & Practice p. 310-316)

NON-DISCLOSED INCUMBRANCE REVEALED

Should it have been disclosed?
  • If it was latent and not clearly observable on personal inspection, then yes it should have

  • The seller has a duty of disclosure (SCPC 9.1.2)

  • So, the buyer will have a cause of action for breach of this element of the contract

T&F NOTE buyer has no rightof action against sellerin relation to an incumbrance under the implied covenants for title, provided thattheincumbrance has been properly disclosed in the contract.

Was the contract made by deed?
  • If yes, then LA 1980 gives you 12 years (limitation Period to bring a claim)from date of breach

  • If not, then LA 1980 gives you 6 years (limitation Period to bring a claim)from date of breach

  • Check the contract itself for any other limitation

What remedies are available for breach of the contract?

P310

Damages (SCPC 9.1.2) P310

  • Buyer is only entitled to damages if there’s a material difference in the value of the land

  • If B defaults and S makes loss on a resale, then S can claim damages

  • If B defaults and S makes a profit on a resale, then this must be taken into account

  • Damages will be awarded under the Hadley v Baxendale principle (losses naturally flowing from the breach) and any reasonably foreseeable consequential loss that was foreseeable when the contract was made

  • NOT claim for: mental distress or pre-contract expenditure

Rescission (SCPC 9.2) P312

  • If the value is substantially reduced, rescission is available

  • If error resulted from fraud, misrep. or recklessness, rescission is always available

  • It is the restoration of the parties to their original position by undoing the contract and paying compensation to balance their positions

Specific Performance of the contract

  • It is an equitable remedy and therefore entirely at the discretion of the court however, orders for Specific Performance are not uncommon since no two pieces of land are identical and damages may not be therefore adequate or appropriate compensation for breach

Remedy expressly contained in the Contract

  • The remedy provided in the contract may be recession, damages or some other remedy.

Quantum Quantum = contract price less market price at the date of the breach plus actual financial loss suffered as a result of the breach
Mitigation Claimant must show that he has made reasonable steps to mitigate his loss
Credit Must be given for compensation paid under 9.4 or for a deposit forfeited
Misrep. T&F NOTE A buyer may have a cause of action against the seller for negligent misrepresentation under the Misrepresentation Act 1967. The action would be for rescission of the contract and damages. But, if contract incorporated SCPCs, SCPC 9.1 limits the remedies available to the buyer.

THREATEN NOT TO COMPLETE

While this isn’t a breach of contract, it would be prudent for the other party to apply to court for a Specific Performance Order (“SPO”) requiring the other party to complete their obligations under the contract (Hasham)

Note that SPO will not be awarded where: damages in lieu would be adequate (s.50 SCA); a third party has acquired an interest in the property; the seller cannot make good title to sell

Late Completion

(SCPC 9.3) P310 Any delay will result in a breach of contract entitling the injured party to compensation for the period between completion date and actual completion and any damages for any loss suffered as a result of the delay (Raineri v Miles (1981)) but will not entitle him to rescind the contract (SCPC 9.3.1), unless time was of the essence. After notice to complete has been served (SCPC 8.8.1) party at fault will have 10 working days to complete (SCPC 8.8.2). If party at fault continues to delay completion even after Notice (notice makes “time of the essence” a condition of the contract binding on both parties) the innocent party may rescind the contract (SCPC 9.5 (for buyer)) and (SCPC 9.6 (for seller)) and damages etc (Hadley v Baxendale (1854)) may be awarded to the innocent party. Apply to the facts: are there any other buyers around to sell to? What condition is the property market in? See diagram (based on SCPC not SC):

Calculating Compensation: at the Contract Rate (1.1.1(e))
Purchase price 1,000,000
Less deposit (100,000)
Balance due 900,000 Check the contract to see what was the agreed interest rate, otherwise apply 4.5% (Law Society’s rate) under SCPC 1.1.1(e)

Interest = 900,000 x 8.5%

365 (for daily rate)

209.59
Daily rate for this e.g. 209.59 client may wish to pay it if he has a better purchase alternative and can afford to pay the compensation and damages for late completion.
Late Completion steps from SCPC Standard Commercial Property Conditions
1. Is there going to be late completion? 2. Serve notice to complete 3. Failure to comply with the notice to complete.

SCPC 9.3 Late Completion

9.3.1 If Buyer defaults in performing its obligations under the contract and completion is delayed, buyer is to pay compensation to the seller.

9.3.2 Compensation is calculated at the contract rate on the purchase price (less any deposit paid) for the period between completion date and actual completion, but ignoring any period during which the seller was in default.

9.3.3 Any claim by the seller for loss resulting from delay completion is to be reduced by any compensation paid under this contract.

9.3.4 Where the sale is not with vacant possession of the whole property and completion is delayed, the seller may give notice to the buyer before the date of actual completion, that it will take the net income form the property until completion as well as compensation under condition 9.3.1

** apart from 9.3.2 (compensation) the innocent party may also get damages for breach of contract (e.g. of damages: having to pay mortgage fees, interests)

8.8 Notice to Complete

8.8.1 At any time on or after completion date, a party who is ready able and willing to complete may give the other a notice to complete.

8.8.2 The parties are to complete the contract within ten working days of giving a notice to complete, excluding the day on which the notice is given. For this purpose, time is of the essence of the contract.

9.5 Buyer’s failure to comply with notice to complete

9.5.1 If the buyer fails to complete in accordance with a notice to complete, the following terms apply.

9.5.2 The seller may rescind the contract, and if it does so:

a) it may

(i) Forfeit and keep any deposit and accrued interest on the deposit.

(ii) Re-sell the...

Unlock the full document,
purchase it now!
Property Law and Practice

More Property Law And Practice Samples

Acting For Lender And Buyer Notes Alienation Notes Alienation Leases Model Answer N... Alterations Clauses Notes Assignment Underletting Notes Completion And Post Completion N... Completion Notes Completion Notes Completion Notes Conduct Crib Sheet Notes Conduct Same As Conduct Note In... Contract Conditions Notes Conveyancing Forms Notes Covenants Notes Dealing Notes Delayed Completion Diagram Notes Drafting A Contract Diagram Notes Drafting A Lease Notes Drafting And Exchange Of Contrac... Finance And Surveys Notes Forfeiture Leases Model Answer N... Freehold Contract Amendments Mod... Freehold Registered Land Notes Freehold Unregistered Land Notes Grant Of A Lease, Assignment And... Initial Steps In A Property Tran... Insurance And Repair Notes Investigating Title Diagram Notes Investigation Of An Unregistered... Investigation Of A Registered Ti... Landlord's Consent For Alienatio... Landlord's Remedies For Breach N... Leasehold Notes Leasehold Management Alienatio... Leaseholds Procedure Notes Leasehold Transactions Notes Lease Landlord's Remedies For Te... Lease Open Market Rent Review Notes Lease Rent Review Provisions An... Licences Notes Methods Of Exchange Exchange Of... Misrepresentation In A Property ... Official Copies Analysis Notes Planning Permission Notes Pre Completion, Completion And P... Precontract Searches And Plannin... Pre Contract Searches Notes Pre Contract Searches Notes Pre Exchange, Exchange Of Contra... Professional Conduct In Plp Notes Professional Conduct Issues Notes Protected Tenancies Notes Registered Title Investigations ... Registered Title Search Ws2 T... Register Of Title Notes Remedies For Breach Of Lease Cov... Rent Review Notes Rent, Service Charge & Rent Revi... Repair Insurance Leases Model ... Repair, Rent, Service Charge & I... Residential Conveyancing Notes Results Of Searches And Enquirie... Sale And Purchase Of Freehold Notes Sale And Purchase Of Freehold Ws... Sale Of Part Notes Sale Of Part Notes Scpc V Sc Table Ws 4 Itutorial ... Security Of Tenure Diagram Notes Security Of Tenure Notes Security Of Tenure Leases Model ... Termination Clauses Lta 1954 C... The Contents Of A Lease Notes Unregistered Land Diagram Notes Unregistered Title Crib Sheet Notes Unregistered Titles Notes Unregistered Transactions Notes Vat And Commercial Property Notes